Cutover Readiness

Go-live readiness per wave: UAT, reconciliation, rollback, go / no-go and hypercare

ASAdmin User

Wave

Wave 1 (Pilot)

38 objects

Validation

92%

Reconciliation

78%

Go / No-Go

Conditional Go

Hypercare

22 Jun 2026

22 Jun 2026 – 06 Jul 2026

Wave Readiness Gates

WaveUAT statusValidation %Reconciliation %Rollback planComms planGo / No-GoHypercare windowCutover owner
Wave 1 (Pilot)in progress92%78%AvailableReadyConditional Go22 Jun 2026 – 06 Jul 2026Vikram J.
Wave 2not started46%12%DraftDraftPendingPlanned Aug 2026Arjun M.
Wave 3not started0%0%Not startedNot startedPendingPlanned Oct 2026Meera T.
Wave 4not started0%0%Not startedNot startedPendingPlanned Dec 2026Anita G.

Pre-Release Template

Confirm go-live readiness for the wave.

Migration wave
Wave 1 (Pilot)
Business package
Finance
Domain
Finance
Geography
United States
Objects included
47 (45 in scope after rationalization)
Validation status
92% passed — 1 failed check open
Reconciliation status
78% — 1 unresolved exception
UAT sign-off
In progress — AP Finance
Release window
20 Jun 2026, 22:00 – 21 Jun 2026, 06:00 EST
Cutover owner
Vikram J. (Sigmoid) / D. Kowalski (AP IT)
Rollback plan available
Yes — NEO kept warm for 14 days
Communication plan ready
Yes — AP Finance + Reporting CoE notified
Go / No-Go meeting date
18 Jun 2026
Readiness status
Conditional Go

During-Release Template

Cutover runbook execution tracking.

Cutover taskOwnerPlanned startActual startPlanned endActual endStatusIssue / blockerDecision requiredRollback triggeredCommentsLast updated
Freeze NEO writesD. Kowalski20 Jun 22:0020 Jun 22:0220 Jun 22:1520 Jun 22:14CompletedNoNoClean freeze20 Jun 22:14
Final delta ingestionSuresh D.20 Jun 22:1520 Jun 22:1620 Jun 23:3020 Jun 23:22CompletedNoNo412M rows reconciled20 Jun 23:22
Gold rebuild + DQ gateVikram J.20 Jun 23:3020 Jun 23:3121 Jun 01:30In progressAllocation model excludedYes — scope exclusionNoProceeding without allocation metric21 Jun 00:45
Re-point Qlik connectionsAP Reporting CoE21 Jun 01:3021 Jun 03:00Not startedNoNoAwaiting DQ gate21 Jun 00:45
Business smoke testL. Meyer21 Jun 03:0021 Jun 05:00Not startedNoNoAP Finance team on standby21 Jun 00:45

Post-Release Template

Go-live outcome record.

Wave
Wave 1 (Pilot)
Cutover completed
Partially — allocation metric deferred
Production validation status
Passed with exception
Open issues
1 — cost centre allocation model
Rollback used
No
Business impact
Cost centre reporting on legacy NEO for 2 weeks
Go-live approval owner
L. Meyer (AP Finance)
Go-live approval date
21 Jun 2026
Hypercare start date
22 Jun 2026
Final release status
Live with exception